Equity gap in construction contracting: Identification and ramifications

Zhu, L and Cheung, S O (2022) Equity gap in construction contracting: Identification and ramifications. Engineering, Construction and Architectural Management, 29(1), pp. 262-286. ISSN 0969-9988

Abstract

Purpose: This study conceptualizes the equity gap (EG) in construction contracting and examines its impact on project performance. Design/methodology/approach: The identification of EG was first summarized from a literature review. A conceptual framework that included EG elements of information, risks, expected return and power asymmetry was then proposed. A study of the Hong Kong–Zhuhai–Macau Bridge supported the existence of EG. The framework was further refined by incorporation of 21 EG identifications. To examine the reliability of the framework, data were collected from 106 senior project professionals to evaluate the extent to which EG identification occurred in their projects. A Partial Least Square–Structural Equation Modeling (PLS-SEM hereafter) analysis was conducted on the collected data. Findings: The proposed framework was deemed statistically significant. Furthermore, no significant differences were detected between the developer and contractor. The concepts of asset and process specificities suggested that the unaddressed EG may be met with retaliatory behaviors, such as noncooperation, procrastination, opportunism and withdrawal, as the physical works proceed. These behaviors may also hamper project performance. Practical implications: To address the EG ex post, it is suggested that relational incentives to balance the power differential be set, reallocation of risks and return and enhancing task programmability for ease of monitoring and performance evaluation. Originality/value: This study investigates the downside of the EG between the contracting parties. The proposed EG framework informs the project management of critical EG elements and possible methods to narrow the gap ex post. Practical suggestions are also provided to manage construction contracts in general and in the use of incentive schemes to address EG.

Item Type: Article
Uncontrolled Keywords: contracting behavior; equity; interorganizational relationship
Index terms: interorganizational relationship, project management, monitoring, project performance, construction contract, contracting party, Hong Kong, partial least square, conceptual framework, expected return, performance evaluation, methodology, literature review, structural equation modelling, Macau, opportunism
Subjects: business, contract type, practitioner, control systems, economic analysis, data analysis and analytics, research methods, theoretical framing, performance measurement, project management theory and practice, Geography, statistical analysis
Topics: Roles and Professions, Procurement, Business Strategy, Research Practice, Geographical Context, Project Management, Site Management, Organizational Design, Quality Management
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here