Maharjan, S; Shrestha, P P and Srirangam, D (2023) Impact of mobilization costs on schedule performance of highway projects. Engineering, Construction and Architectural Management, 30(5), pp. 2008-2025. ISSN 0969-9988
Abstract
Purpose: The purpose of this study is to determine whether there is a correlation between mobilization costs and project schedule performance of highway projects. In addition to this, the study will also determine if the mobilization costs are helping small or large highway projects in terms of improving the schedule performance. Design/methodology/approach: The data of 206 highway projects were collected from the Department of Transportation of two states with the help of questionnaire survey. The cost, schedule and mobilization costs data were collected. The performance metrics related to construction schedule growth and construction intensity were developed in order to test the research hypotheses: mobilization costs will increase the schedule performance of highway projects. The data were also divided into two groups based on project cost and analyzed to check whether the mobilization costs impact the schedule performance of these highway projects. Spearman's correlation test was conducted to determine the correlation between dependent and independent variables. In addition, a Mann–Whitney test was conducted to determine the difference in medians of construction schedule growth and the construction intensity of these two groups of projects. Findings: One major study finding was that there was no strong linear correlation between the mobilization cost percentage and the construction schedule growth and construction intensity of highway projects. However, the study found the projects that have 9% or more mobilization costs had significantly better schedule growth compared to the projects that have less than 9% mobilization costs. When data were analyzed based on the project size, it was found that this pattern was seen only in large projects costing equal to or more than $5 million. Practical implications: This study's findings have very crucial practical implications to state DOTs contract engineers. This study shows that the highway contract engineers need to provide the right amount of mobilization costs to complete their projects on and before schedule. If the correct amount of mobilization costs is not provided to the contractors, the impact of these mobilization costs on reducing the schedule growth will be negligible. The findings of this study will assist public agency decision makers to complete their projects on or before time by including the mobilization costs provision in the contract. The state DOTs can improve their schedule performance by providing enough financial help to the contractors so that they can improve their cash flows and complete projects successfully within the given timeframe. Originality/value: This paper contributes to the existing body of knowledge by validating the impact of mobilization costs on the schedule performance of highway projects. There has been no empirical study conducted prior to this to identify the role of mobilization costs on reducing the schedule growth of highway projects.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction intensity; construction schedule growth; highway projects; mobilization costs |
| Index terms: | independent variable, engineer, costing, schedule growth, highway construction, empirical study, project cost, survey, schedule performance, cash flow, performance metric, agency, body of knowledge, questionnaire, methodology |
| Subjects: | profession, data collection methods, knowledge management, accounting and finance, civil engineering, economics, research methods, performance measurement, financial management, statistical analysis, sociology, project controls |
| Topics: | Quality Management, Time Control, Cost Management, Engineering Principles, Information Management, Research Practice, Roles and Professions |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here