Application framework for safety-centric construction acceleration planning

Mahdavian, S; Lu, M and Pereira, E (2023) Application framework for safety-centric construction acceleration planning. Engineering, Construction and Architectural Management, 30(4), pp. 1401-1422. ISSN 0969-9988

Abstract

Purpose: Previous research regarding shaping factors and major causes behind accidents in the construction field is reviewed. In particular, a hypothetical model is established to correlate activity time, cost and safety in the context of construction activity acceleration planning. Two demonstration cases are presented to illustrate the proposed theoretical model in the context of critical activity expedition planning. Further, a third case uses a 100-activity project to perform the global level total project time and cost analysis, identifying specific activity acceleration plans that would materialize the shortened total project time at the lowest total project cost. Design/methodology/approach: This research proposes a safety-centric application framework to guide construction acceleration planning at both activity and project levels while taking sufficient preventive measures against safety hazards and accidents. As planning construction acceleration by factoring in safety constraints inevitably drives up cost, it is imperative to control increases in activity costs at the local level in connection with schedule acceleration planning while at the same time not compromising on safety. This research also addresses this critical question through performing global level total project time and cost analysis. Findings: An application framework is proposed for guiding a planner through identifying accident shaping factors, obeying schedule acceleration rules and accounting for safety-related costs in attempts to mitigate hazardous situations on-site at both activity level (local) and project level (global), resulting in (1) minimizing the increase of total project cost in schedule acceleration while at the same time not compromising on safety at individual activities; (2) producing specific execution plans on each individual activity in terms of the amount of time to crash and the associated activity cost. Originality/value: This study is original in developing theories and methods for evaluating the impact of safety constraints upon construction time and cost in activity acceleration planning and project time-cost analysis. The research fills a gap in knowledge in terms of how to factor in sufficient safety constraints while achieving project time and cost objectives on construction acceleration planning at both activity and project levels.

Item Type: Article
Uncontrolled Keywords: acceleration; activity crashing; cost; project planning; safety; schedule
Index terms: schedule acceleration, planner, construction time, acceleration, construction activity, execution plan, methodology, accounting, project planning, cost analysis, crashing, project cost
Subjects: project controls, research methods, economics, financial and cost management, economic analysis, construction operations, profession, control systems
Topics: Business Strategy, Cost Management, Project Management, Research Practice, Roles and Professions, Site Management, Time Control
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here