Productivity scheduling method with maximum constraints

Reis, J S and Lucko, G (2016) Productivity scheduling method with maximum constraints. International Journal of Construction Management, 16(1), pp. 77-93. ISSN 1562-3599

Abstract

This research investigates maximum constraints for linear scheduling via a mathematical model. Maximum constraints are improperly ignored by most current scheduling techniques, especially for linear schedules. However, they can have substantial practical relevance, e.g. to express safety constraints. Therefore the goal is to renew awareness of this type and enable its application to linear schedules with activities of constant productivity. The methodology includes a literature review, followed by an algorithm that relies upon singularity functions. Its first two steps refer to the existing Productivity Scheduling Method, which is extended with mathematical steps to handle maximum constraints correctly. For validation the new algorithm is applied to a schedule example with different scenarios and its peculiarities are discussed. Being able to incorporate maximum constraints will provide project managers with more realistic schedules.

Item Type: Article
Uncontrolled Keywords: algorithm; linear scheduling method; maximum constraint; productivity scheduling method; singularity functions
Index terms: methodology, linear scheduling, validation, literature review, scheduling, mathematical model, productivity, project manager
Subjects: management, research methods, professional development, operations research, data analysis and analytics, profession, mathematical modelling
Topics: Time Control, Roles and Professions, Information Management, Research Practice, Business Strategy
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here