Re-defining flow in construction process for facilitating the identification and quantification of generic overruns existing in construction industry today

Ali, S A A; Arun, C and Krishnamurthy, K (2021) Re-defining flow in construction process for facilitating the identification and quantification of generic overruns existing in construction industry today. International Journal of Construction Management, 21(2), pp. 113-130. ISSN 1562-3599

Abstract

Recent developments in construction research has been in identifying waste in process flow. This extended review article discusses aspects of wastes in relation to lean construction, while suggesting improvements within & beyond the lean portfolio. Further, discussions on recent developments in waste formulations and its impact on construction flow is covered. The article further fine tunes into recommendations within construction process improvement by inductive reasoning whenever possible. The proposals include integrating two currently applied philosophies/methodology in construction management for better identification of waste, i.e. project management & lean construction. This is for facilitating the identifying and quantification of theoretical overruns and waste in process flow. The integration is done by visualizing construction process as a combination of two basic entities: Construction activities (CA) and Construction process support activities (CPSA). Finally, the entire construction process is proposed as a combination of CAs and CPSAs identifying itself as a non Markovian stochastic process which integrates classic project management techniques with lean construction. And in the flow thus modeled, wastes and overruns could be identified separately.

Item Type: Article
Uncontrolled Keywords: construction waste; generic construction; lean construction; project management
Index terms: construction industry, construction waste, project management, project management technique, construction activity, quantification, construction process, integration, methodology, overrun, philosophy, proposal, reasoning, lean construction
Subjects: operations management, project planning, construction operations, waste management, measurement and scaling, building construction, cognitive psychology, project controls, organizational analysis, industry analysis, philosophical studies, research methods, project management theory and practice
Topics: Site Management, Organizational Design, Time Control, Sustainability, Project Management, Research Practice
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here