Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution

Luong, D L; Tran, D H and Nguyen, P T (2021) Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. International Journal of Construction Management, 21(3), pp. 271-283. ISSN 1562-3599

Abstract

The time, cost and quality are crucial, conflicting aspects to construction project management. Tradeoff optimization among project duration (time), project cost, and the project quality within the project scope is necessary to enhance overall construction project benefit. A novel optimization algorithm, Opposition-based Multiple Objective Differential Evolution (OMODE), is presented to solve the time-cost-quality tradeoff (TCQT) problem. This novel algorithm employs an opposition-based learning technique for population initialization and for generation jumping. Opposition numbers are used to improve the exploration and convergence performance of the optimization process. A numerical high-way construction project case study is analyzed to illustrate the use of the algorithm and demonstrate its capabilities in generating non-dominated solutions. Comparisons with non-dominated sorting genetic algorithm (NSGA-II), multiple objective particle swarm optimization (MOPSO), multiple objective differential evolution (MODE) and previous results verify the efficiency and effectiveness of the proposed algorithm. This study is expected to provide an alternative solving methodology for the TCQT problem and help project manager plan construction methods with optimal time-cost-quality tradeoff.

Item Type: Article
Uncontrolled Keywords: differential evolution; multi-objective analysis; opposition; time-cost-quality tradeoff
Index terms: tradeoff, construction method, project cost, genetic algorithm, optimization algorithm, construction project, population, evolution, exploration, methodology, efficiency, case study, project manager, duration, project scope, construction project management, effectiveness
Subjects: project management theory and practice, production management, economics, performance management, algorithms, research methods, decision analysis, building construction, project controls, demography, scope management, profession, data collection methods, environmental science, environmental resource management
Topics: Urban Studies, Digital Applications, Quality Management, Site Management, Time Control, Cost Management, Project Management, Research Practice, Roles and Professions, Risk Management, Sustainability
Descriptive scope: 4 PCTE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here