Sarkar, D; Gohel, J and Dabasia, K (2021) Optimization of ready mixed concrete delivery for commercial batching plants of Ahmedabad, India. International Journal of Construction Management, 21(10), pp. 1024-1043. ISSN 1562-3599
Abstract
This paper is an attempt to develop a delivery schedule model with real time data for a commercial ready mixed concrete (RMC) plant in Ahmedabad city of Gujarat, India. Without a proper delivery schedule, either a truck-mixer would need to wait for the concrete to be placed at site or the construction site would need to wait for the truck-mixer to arrive on time. Developing an optimized dispatching and delivery sequence scheduling would improve the dispatching order of delivery of the RMC through truck-mixers from commercial batching plants to the respective construction sites. In the present research, this problem has been addressed through optimization techniques developed through mixed integer programming. Mixed integer programming considers both discrete and continuous variables which affect the delivery of RMC to the respective construction sites. The delivery scheduling problem was defined by identifying the objective function and the associated constraints. The mixed integer programming code was written with the help of MATLAB software. It has been observed after 101 iterations in MATLAB software that the dispatching sequence 1,2,2,1,1,3,2,3,2,3,3,3 has the least total waiting time of 155.4 min. After validating the same model with real time data, it has been observed that for the above dispatching sequence, the total waiting time is 153 min with one obstruction resulting in a delay of 48 min for the casting of concrete at site. Furthermore, based on the computations, it is recommended that the plant authorities need to increase the number of RMC truck-mixers from five to seven.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | commercial batching plants; construction sites; delay; delivery scheduling; dispatching sequence; optimization; ready mixed concrete; truck-mixer; waiting time |
| Index terms: | optimization technique, real-time data, delivery scheduling, ready mixed concrete, India, construction site, mixed integer, scheduling, computation, programming |
| Subjects: | operations research, work location, materials science, programming, computational methods, mathematical modelling, data management, project controls, Geography, algorithms |
| Topics: | Digital Applications, Time Control, Site Management, Engineering Principles, Research Practice, Geographical Context |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here