A proposal of project management practices in public institutions through a comparative analyses of critical path method and critical chain

Petroutsatou, K (2022) A proposal of project management practices in public institutions through a comparative analyses of critical path method and critical chain. International Journal of Construction Management, 22(2), pp. 242-251. ISSN 1562-3599

Abstract

The term “Project Management Practice” is construed in several ways. For this research, we comply with the project management use of tools and techniques on project’s time and cost (Crawford 2005; Olateju et al. 2011; Abassi and Al-Mharmah 2000). Project scheduling still is based on the traditional methods of critical path method (CPM) and Program Evaluation and Review Technique for the majority of contractors and public institutions. The aim of this work is to critically highlight the reasons under which the use of the Critical Chain Project Management (CCPM) is indispensable for scheduling and monitoring public works by public institutions in Greece. In particular, the conclusions of this study are very important for public institutions that don’t implement modern project management practices, tools and techniques. The methodology is exemplified by the analysis of 27 infrastructure projects. The contracts include 300 km of motorway, 46 km of road tunnels and 20 km of bridges constructed for the Egnatia Motorway in Northern Greece from 2002 to 2012. The results confirms that CCPM can perform better than the traditional method of CPM by achieving less construction time combined with accurate resource levelling in the early stages. The aforementioned procedure results in reduced indirect costs due to project's time reduction and reduced direct costs due to better resource allocation (ensuring “on time” availability of resources). As a conclusion, better financial planning is ensured for both the contracting parties i.e. the contractors and the public institutions. It should be noted that in literature the case studies are rare with very small sample size.

Item Type: Article
Uncontrolled Keywords: critical chain project management; critical path method; infrastructure projects; public institutions; public works
Index terms: monitoring, Greece, proposal, infrastructure project, scheduling, construction time, direct cost, critical chain project management, critical path method, project scheduling, programme evaluation and review technique, financial planning, resource levelling, contracting party, resource allocation, project management, time reduction, project management practice, methodology, comparative analysis, indirect cost, tunnel, case study, sample size, public work
Subjects: operations research, project controls, data analysis and analytics, project planning, cost management, economics, research methods, Geography, practitioner, infrastructure engineering, financial and cost management, control systems, data collection methods, infrastructure and transport systems, resource management, research design and methodology, management, project management theory and practice
Topics: Geographical Context, Time Control, Cost Management, Roles and Professions, Business Strategy, Research Practice, Project Management, Procurement, Engineering Principles, Site Management
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here