Generation, visualization, and evaluation schedule of repetitive construction projects using GIS

Tomar, A and Bansal, V K (2022) Generation, visualization, and evaluation schedule of repetitive construction projects using GIS. International Journal of Construction Management, 22(6), pp. 1104-1119. ISSN 1562-3599

Abstract

Surroundings is a major factor that affects scheduling of a repetitive construction project. But, both the past experience of planner and the commercially available tools are limited to take the effects of surroundings on the developed schedule into consideration. Therefore, geographic information systems (GIS) are used in the current study to consider the effects of surroundings on the schedule of a repetitive construction project. The interactive tool for project scheduling is developed in GIS environment by writing in-house scripts for both non-repetitive and repetitive units. 4D execution sequences along with its surroundings have been developed in GIS by linking schedule of a repetitive project with related 3D components. Hence, the effects of surroundings on the schedule of a repetitive construction project can be considered through using GIS in the current case study. Also, the 4D execution sequence along with its surroundings is used in checking the constructability of the developed schedule. Moreover, it helps in identifying logical errors, missing activities in the schedule, spatial feasibility, and constructability analysis. The developed interactive tool is used for the scheduling of Udaigiri boys hostel (UBH) building, as a case study, and helps the practitioners and planners in scheduling of their repetitive construction projects.

Item Type: Article
Uncontrolled Keywords: 4D; geographic information system; critical path mathod; line of balance; repetitive construction scheduling
Index terms: geographic information system, script, practitioner, project scheduling, case study, constructability, line of balance, planner, visualization, scheduling, critical path, repetitive project, repetitive construction, hostel
Subjects: production management, sociology, project controls, practitioner, operations research, profession, design practice, geographical techniques and analysis, construction type, building construction, data collection methods, construction integration
Topics: Research Practice, Construction Technology, Geographical Context, Roles and Professions, Design Practice, Time Control, Project Management
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here