Assessing the causes of project overruns in tunnel construction projects in Pakistan

Ayat, M; Rehman, H; Qureshi, S M and Kang, C W (2023) Assessing the causes of project overruns in tunnel construction projects in Pakistan. International Journal of Construction Management, 23(11), pp. 1856-1866. ISSN 1562-3599

Abstract

Tunnel construction is considered a bottleneck point in mega construction projects because of higher associated risks and uncertainties. This study is an attempt to identify and rank the causes project overruns in tunnel construction projects in Pakistan and propose a mitigation strategy to minimize their effects. For the given purpose, a total of 32 key causes were obtained from the literature and discussion with a team of experts and practitioners. A web-based questionnaire survey was used for data collection. About 55 complete responses were received from the practitioners working as clients, consultants, and contractors in Pakistan. The identified causes were ranked using frequency, severity, and relative importance indexes. The most important causes were found to be inexperienced and incompetent contractors, ignoring consultants' instructions by contractors, inadequate project estimates, delay in issuance of funds to the contractors, and low bids. This study can be employed for controlling the leading causes of overruns in tunnel construction projects. Moreover, it can serve as a guide in further investigation of the causes of project overruns in tunneling in different countries.

Item Type: Article
Uncontrolled Keywords: causes of project overruns; relative importance index; tunnel construction projects
Index terms: survey, overrun, strategy, relative importance index, questionnaire, practitioner, mitigation, construction project, Pakistan, tunnel construction, estimate, investigation
Subjects: financial and cost management, practitioner, data collection methods, risk assessment, project controls, financial risk, production management, Geography, civil engineering, management
Topics: Risk Management, Roles and Professions, Research Practice, Project Management, Geographical Context, Engineering Principles, Cost Management, Business Strategy, Time Control
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here