An empirical evaluation of the causes leading to binding dispute resolution mechanisms in the quebec construction industry

Arar, A J; Papineau, C and Poirier, E (2024) An empirical evaluation of the causes leading to binding dispute resolution mechanisms in the quebec construction industry. International Journal of Construction Management, 24(7), pp. 761-770. ISSN 1562-3599

Abstract

Construction disputes may arise from various situations and have varied consequences throughout the project life cycle. Whilst previous studies examined the leading causes of disputes, there is still a lack of understanding of the differences between the various disputes in terms of severity, probable implications, and outcomes. Specifically, once disputes reach a stage where they must be resolved through binding dispute resolution methods (DRMs), little research has been conducted to understand the impact of these DRMs on project outcomes. The research presented in this paper sought to establish which causes of disputes lead to binding DRMs. A sequential exploratory research design was adopted. First, interviews were conducted with nine construction experts in Quebec, Canada, to evaluate the potential of linking specific causes of disputes with the escalation to binding DRMs. The second phase involved collecting and analysing data from 94 participants through a survey. The findings revealed that unforeseen changes, lack of communication, ambiguities in contract documents, design errors, and work progress delays were the most commonly associated causes of reaching binding DRMs. The paper concluded that alternative approaches such as relational contracts, team integration, and innovative technology and communication tools should be considered to be used as preventative measures.

Item Type: Article
Uncontrolled Keywords: dispute resolution methods; conflict resolution; construction disputes
Index terms: integration, contract document, survey, interview, resolution, construction industry, construction dispute, exploratory research, dispute, conflict resolution, life cycle, Canada, project outcome, design error
Subjects: professional practice, value management, dispute resolution, project completion, data collection methods, industry analysis, organizational analysis, conflict resolution, Geography, contractual condition, research methods
Topics: Contract Administration, Organizational Design, Legal Issues, Design Practice, Stakeholder Management, Research Practice, Geographical Context, Project Management
Descriptive scope: 4 PCTE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here