Smith, G R and Hancher, D E (1989) Estimating precipitation impacts for scheduling. Journal of Construction Engineering and Management, 115(4), pp. 552-566. ISSN 0733-9364
Abstract
Contract managers are expected to evaluate requests for contract extensions due to abnormal weather. However, they may not have a definition of normal weather impact for comparison. The implicit assumption in a contractor’s time-extension request is that normal weather disruptions are included in the original schedule. While subjective estimates can be prepared for weather impact, analytical approaches have been limited. The development of an analytical technique for evaluating impact will provide a basis for comparing planned and actual weather impact. A conceptual model for evaluating precipitation impact is presented. The method utilizes a Maikov process for prediction of rainfall events, combined with an impact evaluation utilizing basic fuzzy-set operations. The treatment of information for the impact analysis stresses the individual treatment of activities. An example of a calculation is provided to demonstrate the technique. The proposed method provides an opportunity to evaluate normal weather impact to schedules, for planning purposes. If the normal weather impact can be defined, the difficulties of evaluating time-extension requests can be reduced.
| Item Type: | Article |
|---|---|
| Index terms: | estimate, impact analysis, precipitation, estimating, weather, scheduling, contract manager, rainfall |
| Subjects: | operations research, data analysis and analytics, financial and cost management, air quality, climate science, practitioner |
| Topics: | Time Control, Cost Management, Research Practice, Roles and Professions, Sustainability |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here