Critical success factors in winning BOT contracts

Tiong, R L; Yeo, K T and McCarthy, S C (1992) Critical success factors in winning BOT contracts. Journal of Construction Engineering and Management, 118(2), pp. 217-228. ISSN 0733-9364

Abstract

The build-operate-transfer (BOT) concept represents a step forward in meeting the needs of developing countries for more capital investments in infrastructure and industrial construction. However, for a private-sector consortium bidding for a BOT concession, the road to winning a major BOT contract is not easy. The consortium must be willing to take calculated risks and at the same time be adaptable to changing demands and circumstances in the host country. This paper describes the importance and characteristics of six critical success factors (CSF) that are vital for project sponsors in their endeavors to win lucrative BOT contracts. These factors are: entrepreneurship, picking the right project, a strong team of stakeholders, an imaginative technical solution, a competitive financial proposal, and the inclusion of special features in the bid.

Item Type: Article
Index terms: developing country, project sponsor, proposal, capital investment, critical success factor, bidding, consortium, industrial construction, entrepreneurship, build-operate-transfer
Subjects: business, control systems, contractual arrangements, project planning, bidding, economic analysis, development economics, partnership management, sociology, building construction
Topics: International Construction, Procurement, Stakeholder Management, Project Management, Engineering Principles, Business Strategy
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here