Construction of Akashi-Kaikyo bridge west anchorage

Furuya, N; Yamaoka, R and Paulson, B C (1994) Construction of Akashi-Kaikyo bridge west anchorage. Journal of Construction Engineering and Management, 120(2), pp. 337-356. ISSN 0733-9364

Abstract

The Akashi-Kaikyo suspension bridge, with a central span of 1,990 m, will soon become the world’s longest single span. In total, some 1,420,000 m3 of concrete will go into two piers and two anchorage substructures. Two steel towers will rise to 297 m above sea level; 200,000 t of steel will form the superstructure. Twin cables, each 1.1 m in diameter, will support up to 118,000 tons. Design criteria should enable the bridge to survive earthquakes of magnitude 8.5 and winds of over 80 m/s. Started in 1988, it is scheduled for completion in 1998 at a cost of $3 billion. This paper begins with an overview of the bridge, but concentrates on construction of the west anchorage (1A), recently completed. This anchorage was built within a 75.5-m deep, 2.2-m thick concrete slurry wall. Mass concrete within the 85-m diameter retaining wall was placed from a depth of 64.5 m using roller-compacted concrete. Design details, production methods, automated instrumentation, and data-collection systems are described.

Item Type: Article
Index terms: retaining wall, anchorage, earthquake, instrumentation
Subjects: environmental hazards, structural engineering, analytical methods
Topics: Sustainability, Engineering Principles
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here