Linear scheduling model: Float characteristics

Harmelink, D J (2001) Linear scheduling model: Float characteristics. Journal of Construction Engineering and Management, 127(4), pp. 255-260. ISSN 0733-9364

Abstract

By definition, any activity not on the critical path must have float. The concept of float in the critical path method relates to how long an activity can be delayed before it becomes a critical activity. For linear construction activities, however, the concept of float is somewhat different from that of traditional scheduling techniques. Rather than start time and duration being the main attributes of float, production rate is a more fundamental attribute of a linear activity. As such, for float to be meaningful for a linear activity, it must be reflective of the activity's major characteristic. Rate float captures this characteristic and presents information to construction planners and managers in terms that are meaningful for linear projects. This paper describes rate float as it applies to the linear scheduling model developed by Harmelink and Rowings in 1998.

Item Type: Article
Index terms: scheduling, linear construction, linear scheduling, duration, manager, critical path method, critical path, construction planner
Subjects: project controls, operations research, practitioner, building construction
Topics: Time Control, Engineering Principles, Roles and Professions
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here