Network creation and development for repetitive-unit projects

Yi, K J; Lee, H S and Choi, Y K (2002) Network creation and development for repetitive-unit projects. Journal of Construction Engineering and Management, 128(3), pp. 257-264. ISSN 0733-9364

Abstract

Network scheduling is typically performed in three phases - network creation, analysis, and development. Although the critical path method (CPM) constitutes a well-established logic in network analysis, human intuition and experience are required for the creation and development of the network. Because of this, a variety of alternative CPM networks can be created in scheduling the same project. The use of the most desirable network can lead to a considerable reduction in the duration of the projects. This can be achieved by accurately identifying activities and linking them in an appropriate manner. Many researchers insisted that network scheduling lacks efficiency in scheduling repetitive-unit projects. Because of this, many scheduling methods have been developed to model such types of projects. However, most are not network based and require a large amount of input data, although most leading scheduling software remains network based and field engineers desire networklike forms of the schedule. In an effort to overcome this limitation, this paper presents a procedure for creating and developing networks for repetitive-unit projects. This network-based model incorporates a two-dimensional arrangement of activities, resource-space coordinates, for ease in creating a network and optimizes the activity linkage, thus resulting in the most desirable results. The model is applied to a typical repetitive-unit project to illustrate the use and capabilities of the model. The model can serve as an aid for inexperienced schedulers in creating a network as well as its optimization. An experienced scheduler can also check the desirability of his or her own created network via the use of this model.

Item Type: Article
Uncontrolled Keywords: networks; project management; scheduling
Index terms: network scheduling, project management, duration, efficiency, network analysis, engineer, linkage, intuition, critical path method, scheduling, scheduler
Subjects: project management theory and practice, performance management, project controls, cognitive psychology, practitioner, profession, business, data analysis and analytics, operations research
Topics: Roles and Professions, Business Strategy, Project Management, Research Practice, Time Control, Quality Management
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here