Constralnt-based planning with integrated production scheduler over internet

Chua, D K H; Shen, L J and Bok, S H (2003) Constralnt-based planning with integrated production scheduler over internet. Journal of Construction Engineering and Management, 129(3), pp. 293-301. ISSN 0733-9364

Abstract

Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. The present means of look-ahead planning do poorly in resolving hidden constraints in the supply chain and information flow. Accordingly, work plans are vulnerable to the uncertainties that result in flow variation. It has been realized that reducing and eliminating critical constraints through better means of look-ahead planning are the keys to achieving reliable workflow and, consequently, increased productivity. This paper presents a constraint-based planning tool, Integrated Production Scheduler (IPS), to enhance planning reliability while adopting lean construction principles and the theory of constraints. Unlike the critical path method, the IPS models two additional types of constraints related to resource supply and information exchange. It employs four activity buffers: working, shielding, pulling, and screening for managing critical constraints and shielding the production from uncertainties. The implementation of the IPS is prototyped as a distributed scheduling system using Internet technologies such as Java and XML. It facilitates setting up a transparent project management environment where faster communication and active collaboration among project members are achievable.

Item Type: Article
Uncontrolled Keywords: constraints; internet; scheduling
Index terms: shielding, critical path method, screening, scheduling, buffer, internet, theory of constraints, lean construction, variation, workflow, construction process, scheduler, information flow, implementation, productivity, collaboration, information exchange, project management, transparency
Subjects: financial risk, contractual arrangements, information systems, management, professional development, practitioner, operations research, safety engineering, project management theory and practice, contractual condition, computing systems, building construction, data science
Topics: Organizational Design, Human Resources, Engineering Principles, Site Management, Contract Administration, Roles and Professions, Procurement, Cost Management, Digital Applications, Project Management, Information Management, Business Strategy, Time Control
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here