Production system loading-cycle time relationship in residential construction

Bashford, H H; Walsh, K D and Sawhney, A (2005) Production system loading-cycle time relationship in residential construction. Journal of Construction Engineering and Management, 131(1), pp. 15-22. ISSN 0733-9364

Abstract

Production home building possesses characteristics similar to manufacturing processes, such as the construction of more or less similar houses repeatedly and a growing demand for mass customization of homes. As a result of these similarities, larger home-builders often attempt to view their production system as an assembly line process. However, the management tools generally utilized by these home builders are those used in other sectors of the construction industry, such as critical path method scheduling, cost estimating, and earned value analysis. These management tools do not provide an explanation or control/prediction tools for many undesirable situations that arise during home building, such as increasing cycle time which slows delivery of product to consumers and increases project capital costs, and increasing amounts of work in process that increases capital investment and thereby decreases company financial performance. In order to bring better management tools to the residential construction industry, this study examines relationships between cycle time, work in process, system throughput, new construction starts, and the capacity of the production system using building permit data for new single family homes in Chandler, Ariz. The applicability of Little's law, a basic equation used in factory production management models, to a residential production system is examined. This study shows a definite, predictable relationship between cycle time, work in process, and production system throughput. It provides a pathway for further study of production system characteristics that have historically not been included in construction management models, with the expectation of developing new construction management tools that will account for more of the characteristics of construction production systems that affect project performance and company financial performance.

Item Type: Article
Uncontrolled Keywords: Arizona; buildings; residential; production planning; project management; time factors
Index terms: assembly line, project performance, residential construction, project management, construction production, home building, construction industry, loading, mass customization, manufacturing process, earned value analysis, financial performance, critical path method, production system, scheduling, capital investment, cost estimating, capital cost, production management, builder, production planning
Subjects: industry analysis, construction integration, business analysis, accounting and finance, manufacturing engineering, project management theory and practice, operations management, operations research, financial and cost management, project delivery, economic analysis, construction operations, construction type, practitioner
Topics: Construction Technology, Roles and Professions, Engineering Principles, Research Practice, Project Management, Business Strategy, Cost Management, Time Control, Site Management
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here