Finance-based scheduling: Tool to maximize project profit using improved genetic algorithms

Elazouni, A M and Metwally, F G (2005) Finance-based scheduling: Tool to maximize project profit using improved genetic algorithms. Journal of Construction Engineering and Management, 131(4), pp. 400-412. ISSN 0733-9364

Abstract

Contractor's ability to procure cash to carry out construction operations represents a crucial factor to run profitable business. Bank overdrafts have always been the major source to finance construction projects. However, it is not uncommon that bankers set a limit on the credit allocated to an established overdraft. Bankers' interest rates and consequently contractors' financing costs are basically determined based on the allocated credit limits. Furthermore, project indirect costs are directly proportional to the project duration which is affected by the allocated credit limit. Thus, the credit limit affects project financing costs and indirect costs which in turn affect project profit. However, finance-based scheduling produces financially executable schedules at specified credit limits while maintaining the demand of time minimization. Thus, finance-based scheduling provides a tool to control the credit requirements. This control enables contractors to negotiate lower interest rates which reduce financing costs. Thus, finance-based scheduling enables contractors to reduce project indirect costs and financing costs. This paper utilizes genetic algorithm's technique to devise finance-based schedules that maximize project profit through minimizing financing costs and indirect costs.

Item Type: Article
Uncontrolled Keywords: algorithms; computer aided scheduling; financial management; optimization models
Index terms: duration, construction operation, indirect cost, financial management, financing, interest rate, construction project, profit, scheduling, genetic algorithm, minimization
Subjects: economic analysis, construction operations, operations research, production management, algorithms, cost management, project controls
Topics: Digital Applications, Time Control, Site Management, Business Strategy, Project Management, Procurement
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here