Graham, L D; Smith, S D and Dunlop, P (2005) Lognormal distribution provides an optimum representation of the concrete delivery and placement process. Journal of Construction Engineering and Management, 131(2), pp. 230-238. ISSN 0733-9364
Abstract
The process of concrete supply and delivery exhibits traits of random nature, which render control arduous. This random nature allows concrete placement operations to be considered as a stochastic system and therefore cannot be analyzed by deterministic techniques. In modeling the process realistically, it may be necessary to recreate the variability through fitting a sufficiently flexible theoretical probability distribution to observed data. There is a significant body of work relating to the probability distributions which represent general construction activities. However, there is a lack of literature aimed at determining the optimum representative of the concrete placement process. Therefore, the aim of this paper is to identify a sufficiently flexible representative of this process. To this end, construction data were collected from a number of concrete pours in Scotland, U.K. To identify a suitable distribution in this context, a computer package, PDFit, is presented. It is founded upon the production of probability density functions of select theoretical probability distributions plotted against the histogram of the input data. The principal method of assessment is a visual comparison of the shape of the probability density function and the input data histogram. This paper presents the lognormal distribution as a sufficiently flexible theoretical probability distribution to represent the concrete placing process.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | concrete placing; probability density function; probability distribution; stochastic processes; United Kingdom |
| Index terms: | placement, United Kingdom, Scotland, placing, variability, modelling, concrete supply, package, density, probability distribution, construction activity |
| Subjects: | construction logistics, construction operations, contractual arrangements, analytical methods, Geography, concrete and cementitious materials, management, statistical analysis |
| Topics: | Site Management, Urban Studies, Human Resources, Supply Chain Management, Procurement, Geographical Context, Research Practice, Construction Materials, Engineering Principles |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here