Impact of change's timing on labor productivity

Ibbs, W (2005) Impact of change's timing on labor productivity. Journal of Construction Engineering and Management, 131(11), pp. 1219-1223. ISSN 0733-9364

Abstract

There are many types of construction changes and each type can have an effect on labor productivity. To a certain extent though the specific type of change is not as important as the mere presence of the change and, as analyzed in this paper, the timing of that change. The research reported in this paper reaffirms that project change is disruptive and detrimental to labor productivity. Data from 162 construction projects were statistically analyzed and a series of three curves are presented in this paper, representing the impact that change has on the labor productivity for early, normal, and late timing situations. The projects are a representative sample of the industry, involving a wide range of sizes, different delivery systems, and industry sectors. Late change is more disruptive of project productivity than early change, all other things being equal. The implications and benefits of this research are clear: if changes are necessary, they should be recognized and incorporated as early as possible. Practitioners can use these data and curves for either forward pricing or retrospective pricing of changes. Other researchers can use these findings to test their own findings and to explore timing issues in further detail.

Item Type: Article
Uncontrolled Keywords: cost control; dispute resolution; labor; productivity; scheduling
Index terms: pricing, dispute, productivity, labour productivity, presence, resolution, scheduling, industry sector, cost control, construction project, practitioner
Subjects: dispute resolution, practitioner, financial and cost management, economic analysis, environmental science, operations research, production management, management, industry analysis, conflict resolution
Topics: Sustainability, Stakeholder Management, Roles and Professions, Project Management, Research Practice, Business Strategy, Cost Management, Site Management, Time Control, Legal Issues
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here