Fundamental principles of site material management

Thomas, H R; Riley, D R and Messner, J I (2005) Fundamental principles of site material management. Journal of Construction Engineering and Management, 131(7), pp. 808-815. ISSN 0733-9364

Abstract

This paper was written to fill a void created by the absence of fundamental principles of site construction management. Efficient material management is essential to managing a productive and cost efficient site. For more than 25 years, the senior author has been observing and writing about inefficient labor productivity practices resulting from poor site material management. Using deductive reasoning, fundamental principles were developed to avoid poor practices. A construction site should be portioned into three areas or zones: semipermanent (exterior) storage, staging areas, and workface (interior) storage. Each has a unique function relative to site material management. Using these areas as a framework, fundamental principles are stated and illustrated using a case study project accompanied by numerous photographs and narratives.

Item Type: Article
Uncontrolled Keywords: construction materials; cost control; project management; resource management
Index terms: construction site, reasoning, narrative, cost control, case study, project management, resource management, labour productivity, construction material
Subjects: financial and cost management, building materials, work location, control systems, data collection methods, cognitive psychology, project management theory and practice, qualitative and interpretive research, management
Topics: Site Management, Cost Management, Project Management, Research Practice, Engineering Principles
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here