Zayed, T M and Halpin, D W (2005) Productivity and cost regression models for pile construction. Journal of Construction Engineering and Management, 131(7), pp. 779-789. ISSN 0733-9364
Abstract
The estimating process of pile construction productivity and cost is intricated because of several factors: unseen subsurface obstacles; lack of contractor experience; site planning; and pile equipment maintainability. This study intends to assess cycle time, productivity, and cost for pile construction considering the effect of the above factors using regression technique. Data were collected through designated questionnaires, site interviews, and telephone calls to experts in different construction companies. Many variables have been considered in the pile construction process. Seven regression linear models have been designed and validated to assess productivity, cycle time, and cost. Consequently, three sets of charts have been developed based upon the validated models to provide the decision maker with a solid planning, scheduling, and control tool for pile construction projects. This research is relevant to both industry practitioners and researchers. It provides sets of charts and models for practitioners' usage to schedule and price out pile construction projects. In addition, it provides the researchers with the methodology of designating regression models for the pile construction process, its limitations, and future suggestions.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction; costs; piles; predictions; productivity; regression models; statistical analysis |
| Index terms: | questionnaire, practitioner, construction project, methodology, construction process, estimating, scheduling, maintainability, interview, construction company, construction productivity, regression model, statistical analysis, productivity |
| Subjects: | operations research, operations management, data science, financial and cost management, data collection methods, organization, practitioner, building construction, statistical analysis, management, maintenance engineering, research methods, production management |
| Topics: | Project Management, Research Practice, Cost Management, Business Strategy, Roles and Professions, Site Management, Time Control |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here