Application of lean concepts and simulation analysis to improve efficiency of drainage operations maintenance crews

Agbulos, A; Mohamed, Y; Al-Hussein, M; Abourizk, S and Roesch, J (2006) Application of lean concepts and simulation analysis to improve efficiency of drainage operations maintenance crews. Journal of Construction Engineering and Management, 132(3), pp. 291-299. ISSN 0733-9364

Abstract

The City of Edmonton's Drainage Operations branch oversees the inspection, maintenance, and repair of the city's drainage network. This network covers an area of 700.6 km2 to serve the city's growing population of nearly 1 million people. The activities performed by this division consume a large amount of funding and are, therefore, receptive to improvements in productivity. The study presented in this paper was conducted to develop improved work methods and engineered productivity standards for the various drainage operations. The study focused on six crews, which accounted for over 25% of the total drainage operations budget. The six crews were divided based on their respective duties: (1) cleaning mains by low pressure flushing (LPF); (2) cleaning mains by high pressure flushing; (3) scheduled mechanical cleaning of catch basins (CBC); (4) inspecting mains by televising; (5) commercial establishment investigation; and (6) service-line rodding and televising. The study utilized the concept of work simplification and focused on two crew activities-LPF and CBC work tasks-to improve crew work methods, to develop an established work standard, and to verify the proposed improvements based on the simulation model's output. These activities are described in greater detail in two case studies. The work measurement concept was implemented to develop engineered productivity standards for the remaining crews in order to improve their productivity as well. This paper describes the application of an industrial engineering philosophy of work measurement-lean production theory-and the technique of simulation analysis to capture current work methods, generate and test alternative methods, and develop new productivity standards for drainage maintenance operations crews.

Item Type: Article
Uncontrolled Keywords: Canada; drainage systems; maintenance; productivity; simulation; time factors
Index terms: inspection, Canada, productivity, case study, efficiency, cleaning, simplification, investigation, funding, lean production, philosophy, simulation analysis, duty, drainage, repair, population
Subjects: contractual role, data collection methods, economic analysis, design analysis, Geography, manufacturing engineering, management, performance management, maintenance engineering, philosophical studies, infrastructure and transport systems, quality assurance, demography
Topics: Research Practice, Geographical Context, Engineering Principles, Business Strategy, Contract Administration, Quality Management, Design Practice, Urban Studies
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here