Predicting construction cost using multiple regression techniques

Lowe, D J; Emsley, M W and Harding, A (2006) Predicting construction cost using multiple regression techniques. Journal of Construction Engineering and Management, 132(7), pp. 750-758. ISSN 0733-9364

Abstract

This paper describes the development of linear regression models to predict the construction cost of buildings, based on 286 sets of data collected in the United Kingdom. Raw cost is rejected as a suitable dependent variable and models are developed for cost m2, log of cost, and log of cost m2. Both forward and backward stepwise analyses were performed, giving a total of six models. Forty-one potential independent variables were identified. Five variables appeared in each of the six models: gross internal floor area (GIFA), function, duration, mechanical installations, and piling, suggesting that they are the key linear cost drivers in the data. The best regression model is the log of cost backward model which gives an R2 of 0.661 and a mean absolute percentage error (MAPE) of 19.3%; these results compare favorably with past research which has shown that traditional methods of cost estimation have values of MAPE typically in the order of 25%.

Item Type: Article
Uncontrolled Keywords: construction costs; estimation; predictions; regression analysis
Index terms: estimation, cost estimating, regression analysis, construction cost, dependent variable, regression model, independent variable, United Kingdom, multiple-regression, duration
Subjects: statistical analysis, Geography, project controls, financial and cost management
Topics: Research Practice, Geographical Context, Cost Management, Time Control
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here