Knowledge-based standard progress measurement for integrated cost and schedule performance control

Jung, Y and Kang, S (2007) Knowledge-based standard progress measurement for integrated cost and schedule performance control. Journal of Construction Engineering and Management, 133(1), pp. 10-21. ISSN 0733-9364

Abstract

Though the progress of construction projects is most often used as a critical index for effective project management, the method, structure, data, and accuracy of detailed progress measurement may vary depending on specific characteristics of a project. This situation can lead to misinterpretation of the project status, especially under a multiproject management environment. It is also a daunting task for the inexperienced engineers to formulate and monitor the project-specific work packages. At the same time, maintaining very detailed and highly accurate progress information requires excessive managerial efforts. In order to address this issue, this study proposes the concept of standard progress measurement package. Issues for standardization of the work breakdown structure that can embody distinct characteristics of different construction projects are investigated. The proposed methodology facilitates automated formulating of work packages by using a historical database and also automates the gathering of progress information through the use of standardized methods and tools. A case-study project is evaluated in order to examine the practicability of the proposed system.

Item Type: Article
Uncontrolled Keywords: automation; cost control; information systems; integrated systems; knowledge-based systems; project management; scheduling; standardization
Index terms: package, database, knowledge-based system, engineer, standardization, progress measurement, project management, automation, integrated system, schedule performance, scheduling, accuracy, cost control, construction project, methodology, information system
Subjects: data management, project controls, information systems, performance measurement, research methods, automation and robotics, production management, project management theory and practice, professional development, operations research, contractual arrangements, artificial intelligence, financial and cost management, profession, design methods
Topics: Information Management, Research Practice, Project Management, Cost Management, Procurement, Roles and Professions, Quality Management, Digital Applications, Design Practice, Time Control
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here