Productivity aspects of urban freeway rehabilitation with accelerated construction

Lee, E B; Lee, H and Ibbs, C W (2007) Productivity aspects of urban freeway rehabilitation with accelerated construction. Journal of Construction Engineering and Management, 133(10), pp. 798-806. ISSN 0733-9364

Abstract

Over the last 5 years the California Department of Transportation (Caltrans) has completed three experimental long-life urban freeway rehabilitation projects by utilizing a fast-track (accelerated) construction approach of around-the-clock operations under extended closure. This paper presents the fast-track rehabilitation approaches and the as-built production rates of major rehabilitation operations monitored at the three experimental projects. The monitoring results show that the contractor's production rates varied considerably depending upon the construction logistics, material delivery and hauling methods, lane-closure tactics, and/or pavement designs being implemented. A higher production rate and a noticeable "learning-curve effect" were observed when full-width rehabilitation was compared with partial-width rehabilitation, when continuous lane reconstruction was compared with random slab replacements, and when full roadbed closures were compared with partial lane closures. Findings in this study suggest that Caltrans should evaluate project-specific conditions and constraints, which might restrict use of a preferred rehabilitation scheme, by taking production rate variances into account when establishing schedule baselines of construction staging plans and incentive/disincentive contracts for urban freeway rehabilitation projects.

Item Type: Article
Uncontrolled Keywords: fast track construction; highway construction; monitoring; pavements; productivity; reconstruction; rehabilitation; traffic management
Index terms: traffic management, monitoring, construction logistics, variance, highway construction, pavement design, reconstruction, productivity, replacement, rehabilitation project
Subjects: health conditions and diseases, construction logistics, civil engineering, materials science, measurement and scaling, operations management, management, transportation engineering, building construction, control systems
Topics: Site Management, Business Strategy, Research Practice, Supply Chain Management, Engineering Principles, Health and Safety
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here