Critical path segments scheduling technique

Hegazy, T and Menesi, W (2010) Critical path segments scheduling technique. Journal of Construction Engineering and Management, 136(10), pp. 1078-1085. ISSN 0733-9364

Abstract

While the critical path method (CPM) has been useful for scheduling construction projects, years of practice and research have highlighted serious drawbacks that hinder its use as a decision support tool. This paper argues that many of CPM drawbacks stem from the rough level of detail at which the analysis is conducted, where activities' durations are considered as continuous blocks of time. The paper thus proposes a new critical path segments (CPS) mechanism with a finer level of granularity by decomposing the duration of each activity into separate time segments. Three cases are used to prove the benefits of using separate time segments in avoiding complex network relationships, accurately identifying all critical path fluctuation, better allocation of limited resources, avoiding multiple-calendar problems, and accurate analysis of project delays. The paper discusses the proposed CPS mechanism and comments on several issues related to its calculation complexity, its impact on existing procedures, and future extensions. This research is more beneficial to researchers and has the potential to revolutionize scheduling computations to resolve CPM drawbacks.

Item Type: Article
Uncontrolled Keywords: construction; critical path method; float; project management; scheduling
Index terms: critical path, scheduling, level of detail, decision support, project delay, complexity, critical path method, construction project, computation, duration, project management
Subjects: production management, project management theory and practice, systems engineering, project controls, decision analysis, computational methods, technical documentation, operations research
Topics: Digital Applications, Design Practice, Time Control, Engineering Principles, Project Management, Risk Management
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here