Case law and variations in cumulative impact productivity claims

Nguyen, L D and Ibbs, W (2010) Case law and variations in cumulative impact productivity claims. Journal of Construction Engineering and Management, 136(8), pp. 826-833. ISSN 0733-9364

Abstract

Proving and quantifying lost productivity due to cumulative impacts of multiple changes are difficult tasks. This paper presents the most acceptable methods from case law and demonstrates their applications for analyzing the loss of productivity. These methods include earned value analysis, measured mile analysis, and combinations of these two. They are either well established or drawn from recent court and board decisions. A case study is used to illustrate and compare the use of these methods. These methods result in considerably different loss of productivity values though the actual amount (i.e., inefficiency in labor hours) is unique for a particular case and though these methods are often thought to be similar or even the same. How a measured mile analysis and its variants are employed affects the amount of lost productivity estimated. The variants can avoid some drawbacks of measured mile and earned value studies. Nevertheless, which method is more accurate and reliable is difficult to provide for a particular claim. Practitioners should choose between them based on the availability of project records and the nature of changes and cumulative impacts. Practitioners may also employ two or more methods to perform a "sensitivity analysis" of the chosen methods and persuade the other party and/or the jury that their estimate of lost productivity is sufficiently certain.

Item Type: Article
Uncontrolled Keywords: claims; contractors; contracts; court decisions; owners; productivity
Index terms: sensitivity analysis, practitioner, variation, earned value analysis, owner, productivity, case study, case law, estimate
Subjects: environmental hazards, sociology, contractual condition, management, legal systems, financial and cost management, practitioner, data collection methods
Topics: Legal Issues, Contract Administration, Research Practice, Cost Management, Business Strategy, Sustainability, Roles and Professions, Stakeholder Management
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here