Wibowo, A; Permana, A; Kochendörfer, B; Kiong, R T L; Jacob, D and Neunzehn, D (2012) Modeling contingent liabilities arising from government guarantees in Indonesian BOT/PPP toll roads. Journal of Construction Engineering and Management, 138(12), pp. 1403-1410. ISSN 0733-9364
Abstract
By the end of 2010, the Government of Indonesia (GoI) issued a new regulation on government guarantee provision to protect project sponsors from government-related project risks in public-private partnered (PPP) infrastructure development. Whereas the provision of guarantees can help improve the creditworthiness of PPP projects, it also may expose the GoI to considerable fiscal risk as a result of contingent liabilities the GoI incurs when providing guarantees. This requires a systematic contingent liability analysis to understand the full extent of their exposures. The present paper discusses simple and operational methodologies of quantifying payments of guarantees given to PPP toll road projects to protect project sponsors from skyrocketing costs of acquiring land, delays in scheduled toll adjustment, and compensation payments in case of nationalization. The paper also includes extensive modeling of key project risks, i.e., land cost escalation, initial traffic volume, inflation rates, toll adjustment delays, and a nationalization event. The methodologies are tested on a case study of a PPP toll road project in Indonesia implemented under a build-operate-transfer (BOT) arrangement to demonstrate its application. A Monte Carlo-based simulation is performed to estimate two measures of exposures that are the expected and excess payment of each guarantee. Although the discussion is framed within the context of a specific sector and country, the methodologies offered herein can be adopted to other countries and sectors facing similar problems.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | contingent liability; guarantee; Indonesia; risk; simulation; toll road |
| Index terms: | guarantee, liability, project sponsor, toll, infrastructure development, land cost, regulation, inflation, methodology, exposure, case study, Indonesia, build-operate-transfer, road project, compensation, land, modelling, estimate |
| Subjects: | infrastructure engineering, Geography, research methods, public and environmental health, contract structure, transportation engineering, liability law, political science, sociology, dispute resolution, data collection methods, financial and cost management, analytical methods, economic analysis, contractual arrangements, real estate economics |
| Topics: | Urban Studies, Legal Issues, Health and Safety, Cost Management, Business Strategy, Engineering Principles, Geographical Context, Research Practice, Stakeholder Management, Governance, Procurement |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here