Nguyen, L D; Phan, D H and Tang, L C M (2013) Simulating construction duration for multistory buildings with controlling activities. Journal of Construction Engineering and Management, 139(8), pp. 951-959. ISSN 0733-9364
Abstract
Construction schedules are uncertain in nature; therefore, predicting construction duration is a difficult task. Extensive research has proposed mathematical models to predict construction duration based on regression analysis, Monte Carlo method (MCM), and so on. Yet regression analysis cannot capture duration uncertainties. Studies normally use Monte Carlo methods to simulate hundreds to thousands of activities in a project schedule. This can be complicated, time-consuming, and unrealistic because the statistical properties of all the activities cannot be readily determined in practice. Typical construction sequences in condominium building construction were first identified, and then the statistical distributions of controlling activities on the sequences were surveyed. Two-stage questionnaire surveys and goodness-of-fit statistical tests were conducted to achieve the mentioned objectives. Subsequently, a model for predicting the duration of building construction was proposed and applied to a high-rise building project. The results showed that the proposed model reasonably predicted the construction duration for this apartment building. The model fills the gap in knowledge of construction time forecast by introducing the concept of controlling activities to simplify the evaluation of the schedule uncertainty in multistory building construction. This research is beneficial for practitioners to estimate an overall construction schedule of building projects, especially in preconstruction phases.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | critical-path method; high-rise buildings; Monte Carlo method; scheduling; simulation |
| Index terms: | apartment building, building construction, survey, scheduling, mathematical model, high-rise building, statistical test, practitioner, questionnaire, estimate, duration, construction time, regression analysis |
| Subjects: | project controls, building construction, statistical analysis, data collection methods, construction type, mathematical modelling, practitioner, operations research, financial and cost management |
| Topics: | Cost Management, Research Practice, Roles and Professions, Construction Technology, Time Control |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here