Application of time buffers to construction project task durations

Russell, M M; Howell, G; Hsiang, S M and Liu, M (2013) Application of time buffers to construction project task durations. Journal of Construction Engineering and Management, 139(10): 04013008, ISSN 0733-9364

Abstract

For this research, a time buffer is defined as the extra time added during planning to individual task durations to compensate for uncertainty and protect against workflow variation to assure a predictable hand-off to subsequent crews. Although previous research has acknowledged this addition of time buffers, their use in practice has not been studied. This paper reports on what causes people to add and size time buffers. A nationwide survey was administered to project managers, superintendents, and foremen to identify the most frequent and severe reasons for adding time buffers to construction task durations. Forty-seven buffer factors were grouped into nine categories: project characteristics, prerequisite work, detailed design/working method, labor force, tools and equipment, material and components, work/jobsite conditions, management/supervision/information flow, and weather. Contributions to the body of knowledge include (1) identifying the 12 most frequent and severe causes of time buffer; (2) analyzing (understanding) how buffers are viewed differently by foremen, superintendents, and project managers, between trades and between general contractors and subcontractors, and the perception among different levels of experience; and (3) investigating how companies that do not regularly use the Last Planner System and those that do view those factors differently. Additionally, the research quantitatively developed risk profiles of the buffer factors through an integrated risk assessment approach. Understanding the application of time buffers and their associated frequency and severity will help construction managers address potential problem areas and inefficiencies in a prioritized manner.

Item Type: Article
Uncontrolled Keywords: buffer; labor and personnel issues; time; uncertainty
Index terms: project manager, buffer, risk assessment, supervision, duration, labour force, time buffer, personnel, information flow, survey, general contractor, construction manager, construction project, last planner system, variation, subcontractor, weather, workflow, body of knowledge
Subjects: practitioner, control systems, air quality, data collection methods, profession, knowledge management, operations research, financial risk, production management, contractual condition, economics, management, information systems, project controls
Topics: Time Control, Contract Administration, Human Resources, Supply Chain Management, Digital Applications, Sustainability, Roles and Professions, Research Practice, Project Management, Information Management, Business Strategy, Cost Management
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here