Morgado, J and Neves, J (2014) Work zone planning in pavement rehabilitation: Integrating cost, duration, and user effects. Journal of Construction Engineering and Management, 140(11): 4014050, ISSN 0733-9364
Abstract
This paper describes a methodology developed to support decision makers in planning work zones for pavement maintenance and rehabilitation interventions, integrating cost, duration, and user effects. The methodology relies on two key stages. First, a computer model generates the set of feasible options for work zone layouts and schedules, and combines them to include all options for the intervention's planning and undertaking. Subsequently, a multiple-criteria decision model is used to compare all the alternatives included in the previously obtained set using agency cost, duration, and traffic delay as criteria, according to the weightings that correspond to the decision-maker's preferences. It constitutes an advance in the current knowledge by avoiding the prior characterization of each alternative and, based on the novel integration of the mentioned criteria, pointing towards the set of alternatives that merit additional analysis. Two case studies with different traffic levels are discussed, showing the capabilities of this methodology while identifying the most adequate alternatives for each context.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | computer models; construction costs; cost and schedule; highway and road construction; maintenance; pavements; rehabilitation; scheduling; traffic delay |
| Index terms: | construction cost, case study, duration, option, road construction, pavement maintenance and rehabilitation, scheduling, agency, preference, integration, methodology |
| Subjects: | organizational analysis, project controls, decision analysis, sociology, maintenance engineering, research methods, decision-making and reasoning, civil engineering, financial and cost management, operations research, data collection methods |
| Topics: | Risk Management, Engineering Principles, Research Practice, Cost Management, Business Strategy, Organizational Design, Time Control |
| Descriptive scope: | 4 PCTE |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here