Causes of time buffer and duration variation in construction project tasks: Comparison of perception to reality

Russell, M M; Hsiang, S M; Liu, M and Wambeke, B (2014) Causes of time buffer and duration variation in construction project tasks: Comparison of perception to reality. Journal of Construction Engineering and Management, 140(6): 4014016, ISSN 0733-9364

Abstract

Due to the inherent nature of the construction industry, all construction projects have some amount and type of uncertainty. This uncertainty can lead to variation in project task durations from what was originally planned. As a result, construction personnel compensate for the uncertainty by adding a time buffer to absorb variations in the work plan. For the purpose of this research, a time buffer is defined as the amount of time included in task durations to compensate for uncertainty and to protect against variation. Variation is defined as the difference between the planned and actual task duration. Although previous research acknowledges time buffer additions, the root causes for adding a buffer have not been thoroughly researched. A nationwide survey was administered to project managers, superintendents, and foremen to identify the most severe reasons for adding time buffers to construction task durations. The root causes of variation have been previously identified and are used as the comparison benchmark. Contributions to the body of knowledge include (1) comparing and contrasting the overall most severe causes of time buffers with the most severe causes of duration variation to identify disconnects between the perception of concerns about uncertainty and the reality of what causes task duration variations at different levels of management; and (2) the use of factor analysis to quantitatively identify the underlying structure of time buffer factors. The findings of this research will help construction managers understand what drives the need for buffers in their construction schedules and allow them to focus efforts on strategically addressing the most critical areas of concern and uncertainty. Furthermore, the research reveals similarities and disconnects in the effects of uncertainty on planning and task execution.

Item Type: Article
Uncontrolled Keywords: buffer; duration; labor and personnel issues; uncertainty; variation
Index terms: time buffer, personnel, survey, construction personnel, construction manager, variation, construction project, body of knowledge, project manager, buffer, factor analysis, duration, construction industry
Subjects: management, production management, contractual condition, financial risk, project controls, industry analysis, statistical analysis, data collection methods, profession, workforce, operations research, knowledge management
Topics: Roles and Professions, Research Practice, Project Management, Information Management, Cost Management, Contract Administration, Time Control, Human Resources
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here