De Athayde Prata, B; Pitombeira-Neto, A R and De Moraes Sales, C J (2015) An integer linear programming model for the multiperiod production planning of precast concrete beams. Journal of Construction Engineering and Management, 141(10): 04015029, ISSN 0733-9364
Abstract
Unlike conventional beams, which are cast in the construction site, precast beams are cast in a production line in a beam factory. Their use may considerably reduce the completion time of construction projects, making them attractive to public housing. A key factor for the success of their use is the ability of efficiently producing them, which depends on the quality of the production planning. The objective of this paper is to propose an integer linear programming model for the precast concrete beams production problem. It is first shown that this problem is isomorphic to the well-known multiperiod cutting stock problem. The objective function is the minimization of the production loss of a production order, subject to the available capacity of forms used to cast the beams. A case study is presented with data of a real scale instance, so as to demonstrate the applicability of the model in industrial settings. The proposed model was implemented and ran on the CPLEX solver, which reached an optimal solution within an acceptable running time. The results indicate that significant gains may be achieved in terms of reduction of planning time through the application of the proposed model.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | integer linear programming; precast concrete beams; production planning; quantitative methods |
| Index terms: | minimization, production planning, construction site, completion time, quantitative method, construction project, case study, linear programming, public housing, precast concrete, beam |
| Subjects: | data collection methods, construction type, data analysis and analytics, project delivery, building materials, work location, production management, structural engineering, algorithms, project controls |
| Topics: | Engineering Principles, Construction Materials, Research Practice, Project Management, Construction Technology, Digital Applications, Time Control, Site Management |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here