Time-cost performance effect of change orders from accelerated contract provisions

Choi, K; Lee, H W; Bae, J and Bilbo, D (2016) Time-cost performance effect of change orders from accelerated contract provisions. Journal of Construction Engineering and Management, 142(3): 04015085, ISSN 0733-9364

Abstract

Accelerated contract provisions (ACPs) such as cost-plus-time (A+B) and incentives/disincentives (I/D) are increasingly common, yet very little is known about their pure time-cost performance effects on change orders. To fill this large knowledge gap, a two-stage research methodology drawing on 1,372 highway improvement projects completed in California was adopted for this study. The Stage I study investigated the marginal change-order impacts of two ACPs, pure A+B and I/D combined with A+B. How ACP change orders affect projects' time-cost performance was numerically modeled and successfully validated over the Stage II study. The results clearly showed that both ACPs led to more schedule-change and cost-change orders than conventionally contracted projects, whereas I/D combined with A+B performed significantly better than pure A+B in terms of the magnitude of schedule-change orders. This conveys an important recommendation to state transportation agencies (STAs) that A+B be used with an I/D provision. The results and numerical models of this study would help STAs better assess and justify the impact of change orders on the duration and cost of projects, enabling them to more effectively use contingency amounts. Use of the models can also benefit contractors requesting a change order because the models can provide them with advanced knowledge of the probable time-cost growth rates specifically for the pursued ACP.

Item Type: Article
Uncontrolled Keywords: change order; contracting; contracts; decision modeling; highway rehabilitation; regression; validation
Index terms: improvement project, drawing, time-cost performance, validation, numerical model, transportation agency, change order, cost-plus, duration, modelling, research methodology
Subjects: analytical methods, contractual arrangements, technical documentation, modelling and simulation, research design and methodology, transportation engineering, project controls, professional development, contractual condition, production management, quantity surveying
Topics: Information Management, Engineering Principles, Project Management, Research Practice, Risk Management, Procurement, Design Practice, Time Control, Contract Administration
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here