Jung, M; Park, M; Lee, H S and Kim, H (2016) Weather-delay simulation model based on vertical weather profile for high-rise building construction. Journal of Construction Engineering and Management, 142(6): 04016007, ISSN 0733-9364
Abstract
Severe weather can adversely affect the scheduling of construction projects. It is very important to be able to estimate the delay that would result from such severe weather because construction contracts generally differentiate between weather delays that can be anticipated and those that cannot. Only delays caused by abnormal and unforeseeable severe weather are granted a time extension. Normal and foreseeable weather delays in construction contracts are usually estimated as a monthly average of the severe weather days as determined from historical weather data, which are measured at the ground level. In high-rise building construction, however, this approach may be inappropriate because weather conditions generally vary with an increase in altitude and the height of high-rise buildings has become so great that those conditions can actually affect the construction of the upper floors. Therefore, weather delays estimated using this approach could be subject to this error. For such reasons, a simulation model capable of analyzing weather delays with consideration for altitudinal variations in the weather conditions is proposed for high-rise building construction projects. To achieve this goal, the literature addressing the types of weather variables, the threshold criteria causing weather delays, and the duration of weather delays was first reviewed. Then, a weather-generation model using a k-nearest neighbor time-series method and vertical weather profiles was developed to estimate the weather conditions at high altitudes. A simulation model was finally developed by integrating the weather generation model and a construction schedule simulation model by using a discrete event simulation method, and a case study was conducted to validate the results of weather delay estimation and to analyze the degree to which vertical weather variations affect the schedule of building construction projects. The contribution of this study is the proposal of a method based on a vertical weather profile that is capable of reasonably estimating weather delays in high-rise building constructions, and analyzing the pattern of weather delays in building construction projects.
| Item Type: | Article |
|---|---|
| Index terms: | proposal, weather, discrete event simulation, estimation, construction contract, case study, high-rise building, construction project, duration, scheduling, estimate, variation, estimating, building construction |
| Subjects: | modelling and simulation, operations research, production management, financial and cost management, air quality, construction type, building construction, project planning, contract type, data collection methods, contractual condition, project controls |
| Topics: | Time Control, Contract Administration, Cost Management, Procurement, Project Management, Construction Technology, Sustainability, Research Practice |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here