Causes of construction delays in countries with high geopolitical risks

Kadry, M; Osman, H and Georgy, M (2017) Causes of construction delays in countries with high geopolitical risks. Journal of Construction Engineering and Management, 143(2): 04016095, ISSN 0733-9364

Abstract

International construction contractors are increasingly expanding their business into emerging markets that are often characterized by high geopolitical risk. Working in these regions poses unique challenges that lead to unconventional causes for construction delay. As such, this research aims to (1) develop a better understanding of the causes of delays that may be encountered in countries with high geopolitical risks, (2) gauge the relative impact these delay causes are expected to have on project completion, and (3) capture how delay causes are influenced by project and country characteristics. Research findings are based on two distinct data sources: quantitative and qualitative data. First, a window delay analysis is conducted of six project schedules and narratives with extensive quantitative data informed of the probability and impact of various delay causes in countries with high geopolitical risks. This quantitative source was then complemented with qualitative data based on interviewing 18 experts who were involved in 36 projects, which spanned 16 countries with high geopolitical risks. Results of the quantitative and qualitative data analysis were merged to create an integrated delay cause database. This merging helps to leverage the advantages of both approaches, i.e., accuracy of data and breadth of coverage, and enables construction companies to better anticipate the future causes of delay on their international construction projects. For an upcoming project in a country with high geopolitical risk, the database can be used to suggest or predict the most likely causes of delay based on matching the similarity (location and project type) with existing cases. Comparison of results with the literature on construction delay causes in developing countries suggests that there are several delay causes that are unique, and also substantial, in countries with high geopolitical risks. The benefits of this research are broad. The capacity to predict delay causes in future projects in which geopolitical risks are detectable can result in (1) the development of more effective risk response plans, (2) more reliable estimation of contingencies, and (3) establishment of more efficient project control procedures.

Item Type: Article
Uncontrolled Keywords: contracting; project controls; scheduling
Index terms: international construction project, window, narrative, construction delay, delay analysis, risk response, accuracy, construction company, developing country, emerging market, data analysis, scheduling, project control, international construction, causes of delay, estimation, database
Subjects: control systems, strategic management, organization, data analysis and analytics, financial and cost management, economic analysis, operations research, qualitative and interpretive research, professional development, development economics, financial risk, architectural elements, project controls, data management
Topics: Project Management, Research Practice, Information Management, Cost Management, Business Strategy, Time Control, International Construction, Design Practice, Digital Applications
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here