Automated generation of work breakdown structure and project network model for earthworks project planning: A flow network-based optimization approach

Li, D and Lu, M (2017) Automated generation of work breakdown structure and project network model for earthworks project planning: A flow network-based optimization approach. Journal of Construction Engineering and Management, 143(1): 04016086, ISSN 0733-9364

Abstract

The present research proposes an analytical methodology to automatically generate a work breakdown structure (WBS) and a project network model based on activity-on-node (AON), which consists of two stages: (1) optimizing earthwork volume allocation, which is intended to define haul jobs by identifying the most economical combinations of cut and fill cells, thus minimizing the total haul effort in rough-grading operations and (2) according to the optimization results from Stage 1, establishing WBS and defining precedence relationships among jobs in WBS analytically to enable automated generation of the AON project network model. To simplify the newly devised methodology, a flow network-based technique is developed to facilitate earthwork allocation optimization and AON project network generation. Simulation trace, internal validation, and comparison with related established methods were performed for evaluating the effectiveness of the proposed methodology. To reveal limitations inherent in established methods and cross validate the proposed methodology, two established methods were selected, which represent the state of art in the problem domain. Further validation of the new methodology against established ones entails elaborate simulation experiment design by randomly adjusting earth volumes in each cell of the site and varying site size and statistical analysis of simulation outputs. The comparison-based validation shows advantages of the proposed methodology in (1) ensuring practical feasibility of resulting earthmoving job plans and (2) improving achievable productivity performance of construction operations.

Item Type: Article
Uncontrolled Keywords: automation; critical-path method; earthmoving; flow network; project control; project planning and design; work breakdown structure
Index terms: project control, earthmoving, automation, effectiveness, construction operation, statistical analysis, productivity, simulation experiment, precedence relationship, project planning, validation, methodology, project network, earthwork
Subjects: data science, construction operations, project planning, construction methods, operations research, modelling and simulation, control systems, automation and robotics, professional development, management, research methods, performance management
Topics: Digital Applications, Quality Management, Site Management, Time Control, Business Strategy, Project Management, Research Practice, Engineering Principles, Information Management
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here