Optimal scheduling of railway track possessions in large-scale projects with multiple construction works

Li, R and Roberti, R (2017) Optimal scheduling of railway track possessions in large-scale projects with multiple construction works. Journal of Construction Engineering and Management, 143(6): 04017007, ISSN 0733-9364

Abstract

This paper addresses the railway track possession scheduling problem (RTPSP), where a large-scale railway infrastructure project consisting of multiple construction works is to be planned. The RTPSP is to determine when to perform the construction works and in which track possessions while satisfying different operational constraints and minimizing the total construction cost. To find an optimal solution of the RTPSP, this paper proposes an approach that, first, transfers the nominal market prices into track-possession-based real prices, and then generates a schedule of the construction works by solving a mixed-integer linear-programming model for the given track blocking proposal. The proposed approach is tested on a real-life case study from the Danish railway infrastructure manager. The results show that, in 2 h of computing time, the approach is able to provide solutions that are within 0.37% of the optimal one for six different blocking proposals and two alternative construction providers, so it can be used as an effective support tool in the primary planning stage to suggest preferable track possessions within the existing railway services.

Item Type: Article
Index terms: scheduling, construction cost, programming, computing, manager, proposal, construction work, railway track, infrastructure project, case study
Subjects: practitioner, financial and cost management, infrastructure and transport systems, operations management, programming, computing systems, project planning, operations research, data collection methods
Topics: Engineering Principles, Cost Management, Project Management, Time Control, Roles and Professions, Research Practice, Digital Applications
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here