Two decades of performance comparisons for design-build, construction manager at risk, and design-bid-build: Quantitative analysis of the state of knowledge on project cost, schedule, and quality

Sullivan, J; Asmar, M E; Chalhoub, J and Obeid, H (2017) Two decades of performance comparisons for design-build, construction manager at risk, and design-bid-build: Quantitative analysis of the state of knowledge on project cost, schedule, and quality. Journal of Construction Engineering and Management, 143(6): 04017009, ISSN 0733-9364

Abstract

Measuring the performance of design build (DB), construction manager at risk (CMR), and design-bid-build (DBB) delivery methods has been the subject of many construction research studies. The collective results of these studies are difficult to interpret because the studies extend over decades and some show mixed results as to which delivery method offers superior performance. This paper analyzes the current literature on the three most widely used project delivery methods, and combines the quantitative findings for five performance metrics: cost growth, unit cost, schedule growth, delivery speed, and quality. By combining these results, this paper considers a much larger data set of projects, which leads to more representative results and further confidence in the conclusions. The quantitative results from 30 existing studies representing 4,623 projects are combined, their methodologies are compared and contrasted, and are ordered chronologically to highlight temporal trends. Combining the results from current literature and weighting the findings using each study's sample size shows that DB is the most effective in controlling cost growth (+2.8%) as compared with CMR (+5.8%) or DBB (+5.1%). No single delivery method consistently performs better on unit cost. CMR and DB were found to be the most accurate in controlling the schedule variation of a project, with an average schedule growth of +10.2 and +10.7%, respectively, as compared with a much higher +18.4% for DBB. Moreover, DB was found to be superior in delivery speed in all explored studies and continues to increase its advantage over time. The study also highlights methodological inconsistencies in the construction literature, which could be standardized to provide more comparable results among future studies. This paper contributes to the body of knowledge by analyzing two decades of project delivery systems literature to compare the cost, schedule, and quality performance of DB, CMR, and DBB delivery systems.

Item Type: Article
Index terms: unit cost, quantitative analysis, body of knowledge, variation, methodology, project cost, design build, performance metric, future study, project delivery, schedule growth, quality performance, design-bid-build, sample size, delivery method, construction manager at risk
Subjects: contractual arrangements, knowledge management, data analysis and analytics, project delivery, financial and cost management, research design and methodology, project controls, delivery method, contractual condition, performance measurement, research methods, economics
Topics: Time Control, Contract Administration, Quality Management, Procurement, Information Management, Research Practice, Cost Management
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here