Three-variance approach for updating earned value management

Chang, C J and Yu, S W (2018) Three-variance approach for updating earned value management. Journal of Construction Engineering and Management, 144(6): 04018045, ISSN 0733-9364

Abstract

The project management triad consists of scope, time, and cost. In this study, the schedule variance and schedule performance index, in traditional two-variance earned value management (EVM), are proven not proper time performance indicators, and it is suggested to restore the original physical meanings of work performance as work variance (WV) and work performance index. It is found that work performance can equal time performance before the project's planned duration in certain cases. However, the same is not true generally, especially once the project is overdue. An average work rate-based earned time method (ETM) is introduced in this study, which can serve as an alternative approach to estimate project time at completion. Finally, it is suggested that an independent performance measure, WV, be added to EVM, and that a three-variance approach be used to analyze the performance statuses in work, time, and cost integrally of a given project.

Item Type: Article
Uncontrolled Keywords: earned value management; forecasting; project performance; schedule variance; work rate; work/time/cost
Index terms: work performance, schedule performance, estimate, variance, meaning, earned value management, duration, forecasting, project management, performance measure, project performance, time performance
Subjects: sociology, performance measurement, measurement and scaling, project management theory and practice, financial and cost management, project controls, control systems, operations management, prediction and forecasting
Topics: Cost Management, Project Management, Quality Management, Time Control, Research Practice
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here