Performance of highway design-bid-build and design-build projects by work types

Tran, D Q; Diraviam, G and Minchin, R E (2018) Performance of highway design-bid-build and design-build projects by work types. Journal of Construction Engineering and Management, 144(2): 04017112, ISSN 0733-9364

Abstract

The design-build (D-B) project delivery method has been used increasingly by state departments of transportation (DOTs) because of its documented benefits. Many studies have shown the superior performance of D-B projects when compared to traditional design-bid-build (D-B-B) projects. However, these studies often rely on experts' judgments or small sample sizes based on data collected from surveys, interviews, or case studies. There are few, if any, empirical studies that have compared D-B-B and D-B highway project performance by work types. This research analyzed 139 pairs of D-B-B and D-B highway projects built by the Florida DOT. The 139 pairs of projects were classified into five categories of work types: (1) new construction; (2) reconstruction; (3) resurfacing, restoration, rehabilitation (3R) projects; (4) intelligent transportation systems (ITS)-related projects; and (5) miscellaneous construction such as sidewalks, bike lanes, or landscaping. The study employed both parametric and nonparametric statistical tests to compare cost growth, schedule growth, and construction intensity metrics across the five project work types. The results show that D-B projects statistically perform better than D-B-B in terms of cost growth and schedule growth for miscellaneous construction and 3R project work types, respectively. Design-build projects also statistically provide a higher construction intensity (more work put in place) than D-B-B for new construction and reconstruction work types. No statistically significant differences between D-B-B and D-B projects were found for other project work types. This study contributes to the construction engineering and management body of knowledge by providing empirical comparisons between D-B-B and D-B project performance on the basis of different types of work. The findings from this paper may provide guidance for state DOTs and practitioners to select D-B project delivery for specific work types and benchmarks D-B against D-B-B.

Item Type: Article
Uncontrolled Keywords: delivery methods; highways; performance; project types
Index terms: construction engineering, highway construction, empirical study, project performance, schedule growth, project delivery, reconstruction, case study, judgment, delivery method, sample size, design-bid-build, practitioner, restoration, body of knowledge, statistical test, interview, survey
Subjects: project management theory and practice, renovation and retrofit, civil engineering, research methods, engineering methods, statistical analysis, project controls, delivery method, building construction, dispute resolution, practitioner, data collection methods, research design and methodology, contractual arrangements, knowledge management, project delivery
Topics: Engineering Principles, Information Management, Project Management, Research Practice, Roles and Professions, Procurement, Legal Issues, Time Control
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here