Lee, J and Hyun, H (2019) Multiple modular building construction project scheduling using genetic algorithms. Journal of Construction Engineering and Management, 145(1): 04018116, ISSN 0733-9364
Abstract
Modular construction offers several advantages, such as safe working conditions, fast construction, and high-quality end products. The project scheduling of modular construction should consider the time involved in the factory production, transportation, and erection processes of the units given limited resources (e.g., the number of modular units, available transportation, and workers) and project restrictions (e.g., the sequences of manufacturing production and on-site installation). However, current modular construction project scheduling techniques and previous academic approaches cannot deal with the overall project processes and production/on-site installation sequences simultaneously. This is one reason few mass-production multiple projects exist in the manufacturing industry. Moreover, it can lead to inappropriate project management guidelines and fail to minimize the overall project duration. This paper suggests a model for modular construction projects scheduling using a genetic algorithm. The results show that implementing both overall project processes and project requirements is an efficient way to develop a modular construction project schedule. The proposed optimization tool will help project managers allocate resources efficiently and reduce the completion time of multiple projects.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | genetic algorithm; modular building construction; multiple projects; scheduling optimization; sequences of production and on-site installation |
| Index terms: | project management, duration, working conditions, project manager, modular building, completion time, modular construction, construction project, manufacturing industry, genetic algorithm, scheduling, project scheduling |
| Subjects: | operations research, profession, building construction, project controls, industry analysis, algorithms, project management theory and practice, production management, employment law |
| Topics: | Legal Issues, Digital Applications, Time Control, Research Practice, Project Management, Roles and Professions, Construction Technology |
| Descriptive scope: | 2 PC |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here