Tokdemir, O B; Erol, H and Dikmen, I (2019) Delay risk assessment of repetitive construction projects using line-of-balance scheduling and Monte Carlo simulation. Journal of Construction Engineering and Management, 145(2): 04018132, ISSN 0733-9364
Abstract
Although the line-of-balance (LOB) method is widely used for the scheduling of repetitive construction projects, there are only a limited number of studies that deal with the issue of how to incorporate uncertainty in repetitive schedules. In this paper, a delay risk assessment method is proposed for projects scheduled by LOB. In the proposed method, a LOB schedule is prepared considering the target rate of delivery, and then risk scenarios are defined considering the sources of uncertainty and vulnerability of activities. Next, probability distributions are determined for the required number of labor-hours for each activity and for learning rates, and finally, the delay risk of the project is quantified using Monte Carlo simulation. The application of the method, its outputs, and its potential benefits are demonstrated by a hypothetical case study. Moreover, the proposed method is applied to a real high-rise building project and the potential benefits of using a probabilistic LOB schedule at the planning stage are investigated. The findings reveal that the outputs of the proposed method may enable decision makers to estimate delay risk under various scenarios, formulate effective risk response strategies, and prepare contingency plans for resource utilization in repetitive tasks. However, the simplifying assumptions made during the development of the proposed model regarding the relationships between activity durations, risk scenarios, and learning rates may limit its applicability for all project conditions. Yet the method is generic, and its assumptions can be revised in consideration of specific project characteristics and objectives.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction management; delay risk assessment; line-of-balance scheduling; Monte Carlo simulation; repetitive projects |
| Index terms: | probability distribution, Monte Carlo simulation, case study, resource utilization, repetitive project, estimate, duration, risk response strategy, risk assessment, repetitive construction, scheduling, high-rise building, vulnerability |
| Subjects: | financial risk, production management, building construction, project controls, environmental hazards, statistical analysis, data collection methods, construction type, modelling and simulation, operations research, financial and cost management, site logistics |
| Topics: | Construction Technology, Sustainability, Cost Management, Project Management, Research Practice, Site Management, Time Control |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here