Kim, J J; Miller, J A and Kim, S (2020) Cost impacts of change orders due to unforeseen existing conditions in building renovation projects. Journal of Construction Engineering and Management, 146(8): 04020094, ISSN 0733-9364
Abstract
A renovation project generally requires time, money, or costly equipment to examine the existing conditions of a structure. When unforeseen existing conditions are not properly examined, unexpected costs and/or schedule impacts can adversely affect the successful completion of a renovation project. This paper examines whether the cost impact of change orders due to unforeseen existing conditions is significant compared with the cost impacts of all other change orders, and quantifies the impact on the total project costs and the construction trade. Statistical analyses such as t-test and ANOVA were conducted, using information on 517 change orders obtained from 27 building renovation projects. The results show that change orders due to unforeseen existing conditions have significant impacts compared with change orders caused by other reasons, and that the calculated mean cost is higher for change orders stemming from unforeseen existing conditions. The results also show that the concrete trade is most impacted by change orders from unforeseen existing conditions, while the trade with the highest cost impact is heating, ventilating, and air conditioning. This paper investigates the effect of unforeseen existing conditions on the costs associated with change orders. The paper also identifies those construction trades that are more impacted than others and, therefore, require special attention. This knowledge is essential for identifying areas of possible cost overruns and minimizing overruns in building renovation projects.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | change orders; commercial building; construction costs; existing conditions; renovation; statistics |
| Index terms: | project cost, overrun, commercial building, building renovation, air conditioning, statistical analysis, change order, construction cost, cost overrun, renovation, statistics |
| Subjects: | economics, renovation and retrofit, contractual condition, asset management, project controls, environmental engineering, mathematical modelling, construction type, financial and cost management, data science |
| Topics: | Contract Administration, Time Control, Cost Management, Business Strategy, Research Practice, Engineering Principles, Construction Technology, Sustainability |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here