Application of last planner system to modular offshore wind construction

Lerche, J; Neve, H H; Ballard, G; Teizer, J; Wandahl, S and Gross, A (2020) Application of last planner system to modular offshore wind construction. Journal of Construction Engineering and Management, 146(11): 05020015, ISSN 0733-9364

Abstract

The focus of this study is the applicability of the Last Planner System (LPS) to modular offshore wind construction. Following a design science approach, a conceptual model for LPS adapted to modular offshore wind construction was developed, then refined and evaluated in a field study. The field study investigated was an offshore wind project in the Belgian part of the North Sea. Theoretical knowledge from academics as well as practical experience from field experts allowed adjusting LPS to the context of modular offshore wind construction. The case study organization participated in artifact development and evaluated its utility through implementation. Implementation of the developed artifact reduced the project duration by 21% compared to the as-planned original critical path method (CPM) schedule. Because offshore wind projects have tended to substantially overrun their scheduled durations, 21% may understate the actual improvement. Compared to current installation time within the industry, the project made a 36% reduction, measured by average installation time per megawatt. The developed LPS artifact contributes to the body of knowledge by adaptation of LPS to modular construction, and the evaluation shows its usefulness in the context of modular offshore wind construction.

Item Type: Article
Uncontrolled Keywords: application; design science; last planner system; modular construction; offshore wind project
Index terms: critical path method, body of knowledge, last planner system, modular construction, overrun, science, artifact, field study, duration, implementation, adaptation, case study
Subjects: user focus, data collection methods, specialized education, operations research, knowledge management, contractual arrangements, research methods, building construction, sociology, project controls
Topics: Procurement, Construction Technology, Research Practice, Information Management, Time Control, Education, Design Practice
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here