Kitting logistics solution for improving on-site work performance in construction projects

Tetik, M; Peltokorpi, A; Seppänen, O; Leväniemi, M and Holmström, J (2021) Kitting logistics solution for improving on-site work performance in construction projects. Journal of Construction Engineering and Management, 147(1): 05020020, ISSN 0733-9364

Abstract

Material kitting has been proposed as an effective solution to organize just-in-time (JIT) material deliveries around assembly tasks; however, its applicability and impact on construction projects has not been thoroughly studied. The purpose of this research is to evaluate the applicability of kitting by focusing on its impact on work performance and requirements for management. The authors conducted a case study to analyze a kitting intervention in a general contractor and logistics company, comparing four renovation projects in the indoor construction phase with and without kitting. Findings indicate that kitting can stabilize assembly work and increase workplace utilization and on-site labor productivity. However, it requires centralized material logistics, smooth information flow between operations, and subcontractors' commitment to the production model. This research contributes to the connection between material logistics and work performance, suggesting that kitting should be linked to a redesign of the general production model toward a synchronized takt-based production system. The research is limited to four projects.

Item Type: Article
Uncontrolled Keywords: assembly kit; construction logistics; material kitting; renovation projects; work performance
Index terms: case study, renovation, construction logistics, labour productivity, construction phase, redesign, work performance, site work, production system, commitment, general contractor, information flow, construction project, just-in-time, subcontractor
Subjects: construction logistics, design methods, practitioner, data collection methods, site logistics, project delivery, psychology, operations management, production management, manufacturing engineering, management, renovation and retrofit, information systems, lean logistics
Topics: Digital Applications, Design Practice, Supply Chain Management, Organizational Design, Site Management, Engineering Principles, Research Practice, Project Management, Roles and Professions
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here