Sustainable logistics planning in modular integrated construction using multimethod simulation and taguchi approach

Hussein, M; Darko, A; Eltoukhy, A E E and Zayed, T (2022) Sustainable logistics planning in modular integrated construction using multimethod simulation and taguchi approach. Journal of Construction Engineering and Management, 148(6): 04022022, ISSN 0733-9364

Abstract

This study examined logistics planning in the modular integrated construction supply chain (MiC-SC). Existing models overlook two important characteristics of the MiC-SC-the dynamic behavior of its stakeholders, and the uncertain interactions between its activities and resources-making their applicability limited in real practice. The literature also lacks an understanding of which logistics and construction decisions significantly impact the MiC-SC key performance indicators (KPIs) (e.g., project duration, MiC-SC costs, and emissions). Moreover, optimizing logistics and construction decisions to achieve a trade-off between these KPIs is yet to be addressed. This study contributes to the MiC-SC knowledge by (1) developing a multimethod simulation model that captures the dynamic behavior of MiC-SC stakeholders through agent-based modeling and the uncertain interactions between their internal activities and resources using discrete-event simulation and considering more realistic features such as traffic condition, site layout, heterogeneous truck types, and uncertainty of activities duration; (2) integrating the developed model with the Taguchi approach (TA) to identify the significant logistics and construction decisions that impact five KPIs (project duration, construction costs, construction emissions, logistics costs, and logistics emissions); and (3) applying a simulation-optimization (SO) approach to find the near-optimum logistics and construction decisions that maximize the MiC-SC sustainability through minimizing the project duration, total costs, and carbon emissions. The model's applicability was demonstrated using a case study of a high-rise MiC project. The TA analysis highlighted some interactions between logistics and construction decisions, calling for collaborative decision-making between stakeholders. The proposed SO approach could provide them with near-optimum decisions that minimize the project duration, MiC-SC costs, and emissions.

Item Type: Article
Uncontrolled Keywords: agent-based modeling; design of experiment; discrete-event simulation; modular integrated construction; supply chain logistics management; sustainability
Index terms: logistics planning, decision-making, design of experiment, site layout, logistics management, duration, interaction, construction supply chain, construction cost, agent-based modelling, carbon emission, case study, key performance indicator
Subjects: supply chain operations, project controls, decision analysis, behavioral psychology, data collection methods, construction logistics, climate science, modelling and simulation, logistics planning, financial and cost management, project delivery, site logistics
Topics: Cost Management, Research Practice, Project Management, Risk Management, Sustainability, Supply Chain Management, Time Control, Site Management
Descriptive scope: 4 PCTE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here