Discretized cell modeling for optimal layout of multiple tower cranes

Huang, C; Wang, Z K; Li, B; Wang, C; Xu, L S; Jiang, K; Liu, M; Guo, C X; Zhao, X F and Yang, H (2023) Discretized cell modeling for optimal layout of multiple tower cranes. Journal of Construction Engineering and Management, 149(8): 04023068, ISSN 0733-9364

Abstract

Multiple tower crane layout planning (MTCLP) refers to the selection of the types, quantities, and positions of tower cranes and material storage positions. In a construction project, choosing tower cranes with a larger covering radius and lifting capacity can reduce the transportation time of materials. However, it can also simultaneously raise the rental cost and the risk of crane crashes. Determining an optimal multiple tower crane layout plan to achieve high construction efficiency with low cost is still a challenge. Mathematically, MTCLP is a complex combinatorial problem controlled by a number of variables, such as site configuration, building layout, material storage positions, and workload. To precisely describe irregular shaped sites and buildings, this research partitioned the site into unit cells and proposed a cell-based optimization model. For the optimal crane layout plan, the problem was formulated as a mixed integer linear problem (MILP). The model's mathematical constraints comprised coverage of the given positions, the crane's safety distance, sufficient crane capacity, and the utilization ratio. The objectives were to increase the crane coverage ratio while reducing the cost and the working areas overlapped by more than two cranes. Two case studies are presented to demonstrate the effectiveness of the model. The first construction project consisted of seven buildings with irregular shapes. By strictly forbidding the areas to be overlapped by more than three tower cranes, the model successfully obtained the optimal crane layout plan using the Gurobi Optimizer. Compared with the contractor's layout plan, the optimal plan reduced the rental cost by 10.7% and the area overlapped by more than three tower cranes by 4.56%. In the second project, alternative plans were identified by the Gurobi Optimizer and ϵ-constraint method to enhance confidence in selecting the ultimate crane layout plan. The optimization procedure involved (1) optimizing the layout plan with minimum crane cost and maximum coverage ratio, (2) identifying all possible layouts as the Pareto fronts when the coverage ratio could not be raised without increasing the crane cost, and (3) minimizing the areas of crane overlap covered by more than three tower cranes. The effectiveness of the proposed model is also proved by comparing the differences in layout plans caused by "regular"and "urgent"lifting demands.

Item Type: Article
Uncontrolled Keywords: irregular building shape; multiple tower crane layout planning; optimization; overlapping area; tower crane selection
Index terms: tower crane, low cost, case study, efficiency, modelling, effectiveness, workload, mixed integer, configuration, lifting, construction project
Subjects: management, maintenance engineering, performance management, production management, occupational health and safety management, systems engineering, data collection methods, mathematical modelling, bidding, analytical methods
Topics: Quality Management, Human Resources, Research Practice, Project Management, Engineering Principles, Business Strategy, Health and Safety, Procurement
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here